				Redevelopment of the University of Mathematics, Physics, and Chemistry and the Mineralogy Museum and construction of 40 service housing units.
																						
								Delivery : 
								2014													
Complete commission
Project Owner
 EPAURIF
Project Supervision
 Reichen et Robert & Associés
Technical design office: Sechaud & Bossuyt / Otéis
 Façade engineering: VP&Green
 Fire Protection Consultant: Casso&Cie
 Acoustician: AVEL Acoustique
 Economist: Lucigny Talhouet & Associés
 Lighting designers: L’Observatoire 8/18
 Landscaping: RB-Cie
 General contractor: Bouygues Bâtiment
Area
 151,852 m² overall surface area
 107,266 m² net floor area
 Renovated area: 100,740 m²
 New area: 6,526 m²
 Museum: 722 m²
 Exhibition space: 350 m²
 Restroom reception: 144 m²
 Offices, workshops, and various storage areas for the museum: 228 m²
Project value
 €274.3 M tax excluded
Environmental performance
 RT 2005 (thermal regulation)
Photographer
 Luc Boegly
Perspectives
 Platform, Kaupunki
 
				 
				 
				 
				 
				 
				 
				 
				 
				 
				 
				 
				 
				 
				 
				 
				 
				 
				 
				 
				 
				 
				 
				 
				 
				 
				 
				 
				 
				 
				 
				 
				 
				 
				 
				 
				 
						