 
				Scenario of the tower-hospital:
 Building towers is not considered a goal in itself but rather the normal result of a major urban programme that includes the Hôpital Bichat, which is already classified as a high-rise building.
																						
								Delivery : 
								2011													
Drawing up property and technical master plan
PROJECT OWNER
 Assistance Publique – Hôpitaux de Paris (AP-HP)
PROJECT SUPERVISION
 Reichen et Robert & Associés
 Environmental consulting, Technical Design Office all trades, structural, electrical and HVAC: Setec bâtiment
 Hospital consultant: Groupe Montaigne
 Construction economics: LTA
 Hospital planning and specification: Polyprogramme
AREAS
 130,000 m² interior floor area:
 47,000 m² conventional elective-care hospital
 37,000 m² critical and post-emergency care
 22,000 m² outpatient hospital and maternity unit
 24,000 m² “support” functions
 1,200 lits
 
				 
				 
				 
				 
				